STATEMENT OF PROBLEM: During the pre-construction phase of the Delta Township WRRF, the provision and installation of temporary haul roads was unfortunately overlooked. The result of unforeseen costs associated with building these temporary haul roads required large portions of the budget allowance to be used. In ad…
STATEMENT OF PROBLEM: Even after compaction of limestone sand, the concrete trucks would create ruts while crossing the grade. Extra grading would be needed as concrete was being placed to reduce this rutting. COURSE OF ACTION: The limestone sand was replaced with crushed limestone where feasible to provide a m…
Project Phase- Construction/Installation Delivery Method- General Contract-Prime Base Contract schedule was very aggressive, with tooling being installed while demo activities were taking place. This schedule was in the bid documents and we agreed to it. The central area being demolished was isolated within th…