Job #3330 Project: Fedex WCAA Expansion Customer: Shaw Electric STATEMENT OF PROBLEM: In May 2023, CCC had excavated and Shaw Electric had installed a single 4" temporary feed conduit to power trailer city. On January 18, 2024, CCC was excavating in the same area as the temporary feed and hit the 4" temporary …
STATEMENT OF PROBLEM: During the pre-construction phase of the Delta Township WRRF, the provision and installation of temporary haul roads was unfortunately overlooked. The result of unforeseen costs associated with building these temporary haul roads required large portions of the budget allowance to be used. In ad…
Statement of Problem - The building was designed and coordinated in 3D, the civil site work was designed in 2D and not part of the 3D master model. This led to poor coordination between the building/site utility connection points, as well as some utilities and equipment pads which were coordinated incorrectly. …