You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from Pontiac tag

Press Pier Anchor Bolt Cans

Statement of Problem: During the design process CCC was provided with a Rotem drawing with several sheets detailing the press foundation requirements. An enlarged elevation called for a "can" cast into the pier to allow for bolting the press anchor rod (hand hole). The drawing showed the can height at 300mm. Howe…

AE Submittal Return Process & Submittal Review

STATEMENT OF PROBLEM Throughout the job there were critical submittals CCC needed prompt reply on in order to complete work per the schedule. Submittals that were delayed (in this case most notably structural steel submittals) caused schedule delays for CCC in ordering materials/completing the work. While many su…

New Cooling Tower Mechanical/Structural Coordination

Statement of Problem: In the design coordination of the cooling tower cells and the steel support platform, there was a disconnect in the 3D model between JEG and IBI with the actual elevation of the cells. Additionally, JEG changed the piping configuration to the basins and this impact was not discussed with the…

Cooling Tower Pump Room - Water Treatment Chemicals

Statement of Problem: The pump room design had insufficient containment for the two chemicals treating the cooling tower water. This led to a situation where if an accident were to happen and both drums were ruptured, the two incompatible chemicals could potentially mix and produce an adverse gaseous affect (chlo…

Clarification of Building Structural Steel Design Type

Statement of Problem: At bid time GM provided LGR structural reference drawings for their press bay addition. These drawings employed a single-column design concept with a cantilevered bracket to support the crane girders. However, nothing in the RFPS stated that Pontiac had to use a single-column design or copy …

Unknown As-Built Conditions

Statement of Problem: At bid time CCC received the 1950 Albert Kahn facility record drawings of the plant. This set had two foundation drawings, showing two different column foundation types for the plant. One drawing showed all footings, one drawing showed all caissons. It was unknown by GM which was the as-built c…

Press Process Design Coordination with Facility Design

Statement of Problem: There were several issues to where the 2D press drawings provided by Rotem did not show enough detailed information for proper coordination. These included: 1) the press cable trays in pit  2) The platforms and ladders between the presses. 3) D/B team not having a useable press 3D model. …

Lesson Learned Civil Design Coordination with Building 3D Design

Statement of Problem - The building was designed and coordinated in 3D, the civil site work was designed in 2D and not part of the 3D master model. This led to poor coordination between the building/site utility connection points, as well as some utilities and equipment pads which were coordinated incorrectly. …

scroll to top icon