Project Phase: Construction Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: The project has numerous fume hoods and overhead service carriers located throughout the labs, that were pre-wired and pre-plumbed at the factory. These were designed and specified by the lab planner archi…
Statement of Problem: There were several issues to where the 2D press drawings provided by Rotem did not show enough detailed information for proper coordination. These included: 1) the press cable trays in pit 2) The platforms and ladders between the presses. 3) D/B team not having a useable press 3D model. …
Project Phase: Design Delivery Method: General contract-Prime Bus shut downs were not part of the master schedule. This caused a lot of heart ache with the plant as bus plug shutdowns affected other contractor''''s work. The owner did not want bus shutdowns within the master schedule due to anticipated chan…