Project Phase: Construction Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: The project has numerous fume hoods and overhead service carriers located throughout the labs, that were pre-wired and pre-plumbed at the factory. These were designed and specified by the lab planner archi…
STATEMENT OF PROBLEM There were significant delays in obtaining control wiring drawings from the mechanical subcontractor for the cooling tower, the ARUs, and the substation W HV units. This led to several delays with the electrical installation of the unit controls as the electrical subcontractor could not do an…