STATEMENT OF PROBLEM: No determination was provided from KUKA on the anchoring of the Kawasaki Robot RTU (7th axis robot) until the equipment arrived. It was then learned that the holes in the bases were suitable for 5/8 mechanical anchors and not 5/8" chemical anchors since the holes in RTU base were not large enoug…
STATEMENT OF PROBLEM There were significant delays in obtaining control wiring drawings from the mechanical subcontractor for the cooling tower, the ARUs, and the substation W HV units. This led to several delays with the electrical installation of the unit controls as the electrical subcontractor could not do an…
Project Phase: Construction Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: The project has Mott Novaguard fume hoods located throughout the labs. These fume hoods were designed by the lab planning architect, Iron Horse, to have PVC interior liners. During project construction and when the …