Job #3330 Project: Fedex WCAA Expansion Customer: Shaw Electric STATEMENT OF PROBLEM: In May 2023, CCC had excavated and Shaw Electric had installed a single 4" temporary feed conduit to power trailer city. On January 18, 2024, CCC was excavating in the same area as the temporary feed and hit the 4" temporary …
STATEMENT OF PROBLEM Additional floor support is required to support the elec. platform. schedule delay as elec platform cannot be installed until floor is poured. COURSE OF ACTION Poured floor before installing platform (schedule delay). LESSON LEARNED Capture Pontiac AA0 solution and incorporate into drawi…
STATEMENT OF PROBLEM Lacking detailed information for routing (i.e. elevations, dimensions, sections, etc.). Contractor claimed responsibility for system locations, which were already coordinated in 3D environment. COURSE OF ACTION None LESSON LEARNED Work with AE to develop a common understanding of expecta…