STATEMENT OF PROBLEM Crane inspection was not performed prior to turnover. Without an inspection it is difficult to determine if wear or maintenance issues on the crane were from construction or from previous plant use. COURSE OF ACTION None LESSON LEARNED An inspection should be done by the facility contrac…
STATEMENT OF PROBLEM Provided a high level of detail of the existing framing and utility conditions that would not be clear on the as-built drawings. Highlighted areas where framing and utilities could go without impacting process equipment. Reduced engineering time and field interference. COURSE OF ACTION …
STATEMENT OF PROBLEM A checklist was not used to facilitate the turnover of the press bay from Facilities to the Press group. Caused some discussions to be missed. COURSE OF ACTION None LESSON LEARNED Institute the buy-off checklist with meeting on ALL press projects.
STATEMENT OF PROBLEM Not enough direct communication with the plant personnel during design decisions. Lack of understanding of substation work; incorrect door specified; confusion on partition walls and take shelter routes; eyewash station dispute; COURSE OF ACTION None LESSON LEARNED RE&F Co…
STATEMENT OF PROBLEM Shared construction space between facility contractor and press installation contractor. Safety concerns; schedule delay. COURSE OF ACTION None LESSON LEARNED Better understanding of what was coming in and when. CCC worked very well with IICC in coordinating the space.
STATEMENT OF PROBLEM Notes for grout at rails etc. do not reflect as installed. Grout notes on drawings create confusion for installation contractors. It drives cost into the quote and wasted time in clarifications and instruction. COURSE OF ACTION None LESSON LEARNED AE to work more closely with Press Engin…
STATEMENT OF PROBLEM No direct discussion with material handling group led to incorrect door equipment being spec''''''''d. Increased cost due to field order; unhappy customer. COURSE OF ACTION Field order (cost and schedule impact) LESSON LEARNED Better communication with the right parties at…
STATEMENT OF PROBLEM Late addition of owner''''s alternates; Inadequate drawings and write-ups. Unclear to bidders; disparity in costs, or non representative cost. COURSE OF ACTION None LESSON LEARNED Need more clear definition in the drawings and scope write-up.
STATEMENT OF PROBLEM The modification of the existing Sub 4A switchgear to accommodate a new 2000A feed was separated out of the main contract in an effort to reuse available assets and perform work during the 2011 X-mas shutdown. The original timeframe could not be allowed by the plant. Solaris documentation and…
STATEMENT OF PROBLEM Interference between cross bar support pockets and structural steel. Additional cost and delays due to field rework required to make the crossbar pocket fit. COURSE OF ACTION None LESSON LEARNED review engineering & revise drawings