You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from AA3X tag

Failure to Perform Crane Inspection

STATEMENT OF PROBLEM Crane inspection was not performed prior to turnover. Without an inspection it is difficult to determine if wear or maintenance issues on the crane were from construction or from previous plant use. COURSE OF ACTION None LESSON LEARNED An inspection should be done by the facility contrac…

Scanning existing basement in Fairfax & Shreveport

STATEMENT OF PROBLEM Provided a high level of detail of the existing framing and utility conditions that would not be clear on the as-built drawings. Highlighted areas where framing and utilities could go without impacting process equipment. Reduced engineering time and field interference. COURSE OF ACTION …

Press bay turnover checklist and sign-off sheet

STATEMENT OF PROBLEM A checklist was not used to facilitate the turnover of the press bay from Facilities to the Press group. Caused some discussions to be missed. COURSE OF ACTION None LESSON LEARNED Institute the buy-off checklist with meeting on ALL press projects.

Eyewash Station System Cost Savings

STATEMENT OF PROBLEM Plant preference was piped eyewash station; RE&F position to use portable system. Is cost savings justifiable? Unhappy customer; safety/maintenance? COURSE OF ACTION Provided portable eyewash station LESSON LEARNED Continue to provide the portable eyewash stations to align…

Grout Drawings Notes Confusion

STATEMENT OF PROBLEM Notes for grout at rails etc. do not reflect as installed. Grout notes on drawings create confusion for installation contractors. It drives cost into the quote and wasted time in clarifications and instruction. COURSE OF ACTION None LESSON LEARNED AE to work more closely with Press Engin…

Fairfax Owners Alternatives Communication

STATEMENT OF PROBLEM Late addition of owner''''s alternates; Inadequate drawings and write-ups. Unclear to bidders; disparity in costs, or non representative cost. COURSE OF ACTION None LESSON LEARNED Need more clear definition in the drawings and scope write-up.

Lack of Plant Personnel Involvement During Design

STATEMENT OF PROBLEM Not enough direct communication with the plant personnel during design decisions. Lack of understanding of substation work; incorrect door specified; confusion on partition walls and take shelter routes; eyewash station dispute; COURSE OF ACTION None LESSON LEARNED RE&F Co…

Sawcutting Quality Control

STATEMENT OF PROBLEM Multiple instances where existing framing to remain was cut due to incorrect depth set on saw; damaged the integrity, and reduced the capacity of the existing members. Schedule impact for repair; additional engineering; non-standard condition for owner. COURSE OF ACTION Repaired (schedule im…

Coordination of work area with press installer

STATEMENT OF PROBLEM Shared construction space between facility contractor and press installation contractor. Safety concerns; schedule delay. COURSE OF ACTION None LESSON LEARNED Better understanding of what was coming in and when. CCC worked very well with IICC in coordinating the space.

Verify With Owner Notes

STATEMENT OF PROBLEM Should have been coordinated with "Owner" prior to issuing bid drawings; Lazy approach by team to just "copy"; Information was known, and could have been committed to. Many DCRs; schedule delays; cost increase due to field orders COURSE OF ACTION Field orders (schedule delays, cost …

scroll to top icon