STATEMENT OF PROBLEM Tie rod pockets are not included in basement floor layout. Tie rods extend above columns when setting crown. All 10 tie rods have to be guided by hand into the crown. SAFETY -personel must now be working above ground & under crown when it is being lowered. DAMAGE increased risk to tie rod thr…
STATEMENT OF PROBLEM Late addition of owner''''s alternates; Inadequate drawings and write-ups. Unclear to bidders; disparity in costs, or non representative cost. COURSE OF ACTION None LESSON LEARNED Need more clear definition in the drawings and scope write-up.
STATEMENT OF PROBLEM No direct discussion with material handling group led to incorrect door equipment being spec''''''''d. Increased cost due to field order; unhappy customer. COURSE OF ACTION Field order (cost and schedule impact) LESSON LEARNED Better communication with the right parties at…
STATEMENT OF PROBLEM Deviation from the designed guardrail. Missing connection pieces, incorrect member sizes, incorrect height, not submitted in shop drawings. Created potentially unsafe condition; additional time to correct; non-conformance to customer''''''''s requirements. COURSE OF ACTION Repaired …
STATEMENT OF PROBLEM Physical lay down space was less than desired. This is pretty common with press relocation work where the bay of work is the only space available for construction. Physical lay down space was less than desired. This is pretty common with press relocation work where the bay of work is the only…
STATEMENT OF PROBLEM The level on the drawings was good, but could have been a bit heavy. No major impact from the level of details on the bridging documents. COURSE OF ACTION None LESSON LEARNED Because of the level of detail known about the press and supporting details, it allowed for more c…
STATEMENT OF PROBLEM Notes for grout at rails etc. do not reflect as installed. Grout notes on drawings create confusion for installation contractors. It drives cost into the quote and wasted time in clarifications and instruction. COURSE OF ACTION None LESSON LEARNED AE to work more closely with Press Engin…
STATEMENT OF PROBLEM A checklist was not used to facilitate the turnover of the press bay from Facilities to the Press group. Caused some discussions to be missed. COURSE OF ACTION None LESSON LEARNED Institute the buy-off checklist with meeting on ALL press projects.
STATEMENT OF PROBLEM Two tie rod pockets were cored in the wrong location. One dimension provided by the Press Group was transposed incorrectly, which migrated into the contract documents. The holes were cored per the drawings. The discrepancy was not discovered until press install, which caused some schedule del…
STATEMENT OF PROBLEM Need clear expectations of what items are existing. What is to remain, or be removed. Confusion to bidders; cost increase due to field orders. COURSE OF ACTION None LESSON LEARNED Work more closely with AE''''''''s to capture as-built conditions at project completion, and to verify condi…