STATEMENT OF PROBLEM Multiple instances where existing framing to remain was cut due to incorrect depth set on saw; damaged the integrity, and reduced the capacity of the existing members. Schedule impact for repair; additional engineering; non-standard condition for owner. COURSE OF ACTION Repaired (schedule im…
STATEMENT OF PROBLEM Shared construction space between facility contractor and press installation contractor. Safety concerns; schedule delay. COURSE OF ACTION None LESSON LEARNED Better understanding of what was coming in and when. CCC worked very well with IICC in coordinating the space.
STATEMENT OF PROBLEM Should have been coordinated with "Owner" prior to issuing bid drawings; Lazy approach by team to just "copy"; Information was known, and could have been committed to. Many DCRs; schedule delays; cost increase due to field orders COURSE OF ACTION Field orders (schedule delays, cost …
STATEMENT OF PROBLEM The level on the drawings was good, but could have been a bit heavy. No major impact from the level of details on the bridging documents. COURSE OF ACTION None LESSON LEARNED Because of the level of detail known about the press and supporting details, it allowed for more c…
STATEMENT OF PROBLEM The compressed air demand for the two presses and FOL equipment changed after the contract aware. This was in part due to a new system late that was still being worked out in Fairfax, and all of the necessary testing was not complete prior to award. Extra effort for engineering to run through…
STATEMENT OF PROBLEM Interference between cross bar support pockets and structural steel. Additional cost and delays due to field rework required to make the crossbar pocket fit. COURSE OF ACTION None LESSON LEARNED review engineering & revise drawings
STATEMENT OF PROBLEM Need clear expectations of what items are existing. What is to remain, or be removed. Confusion to bidders; cost increase due to field orders. COURSE OF ACTION None LESSON LEARNED Work more closely with AE''''''''s to capture as-built conditions at project completion, and to verify condi…
STATEMENT OF PROBLEM Deviation from the designed guardrail. Missing connection pieces, incorrect member sizes, incorrect height, not submitted in shop drawings. Created potentially unsafe condition; additional time to correct; non-conformance to customer''''''''s requirements. COURSE OF ACTION Repaired …
STATEMENT OF PROBLEM Due to the Paint Shop construction, the previously available laydown space for press parts was eliminated. This was discovered after project award. Required additional design effort and a field order to provide additional pavement for laydown space. COURSE OF ACTION None LESSO…
STATEMENT OF PROBLEM No direct discussion with material handling group led to incorrect door equipment being spec''''''''d. Increased cost due to field order; unhappy customer. COURSE OF ACTION Field order (cost and schedule impact) LESSON LEARNED Better communication with the right parties at…