You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from AA3X tag

Tie Rod Pockets

STATEMENT OF PROBLEM Tie rod pockets are not included in basement floor layout. Tie rods extend above columns when setting crown. All 10 tie rods have to be guided by hand into the crown. SAFETY -personel must now be working above ground & under crown when it is being lowered. DAMAGE increased risk to tie rod thr…

Fairfax Owners Alternatives Communication

STATEMENT OF PROBLEM Late addition of owner''''s alternates; Inadequate drawings and write-ups. Unclear to bidders; disparity in costs, or non representative cost. COURSE OF ACTION None LESSON LEARNED Need more clear definition in the drawings and scope write-up.

Roll Up Door Requirements

STATEMENT OF PROBLEM No direct discussion with material handling group led to incorrect door equipment being spec''''''''d. Increased cost due to field order; unhappy customer. COURSE OF ACTION Field order (cost and schedule impact) LESSON LEARNED Better communication with the right parties at…

Fairfax Incorrect Guardrail Installation

STATEMENT OF PROBLEM Deviation from the designed guardrail. Missing connection pieces, incorrect member sizes, incorrect height, not submitted in shop drawings. Created potentially unsafe condition; additional time to correct; non-conformance to customer''''''''s requirements. COURSE OF ACTION Repaired …

Middle Bay Laydown Area

STATEMENT OF PROBLEM Physical lay down space was less than desired. This is pretty common with press relocation work where the bay of work is the only space available for construction. Physical lay down space was less than desired. This is pretty common with press relocation work where the bay of work is the only…

Level of Detail in Drawings and RFPS

STATEMENT OF PROBLEM The level on the drawings was good, but could have been a bit heavy. No major impact from the level of details on the bridging documents. COURSE OF ACTION None LESSON LEARNED Because of the level of detail known about the press and supporting details, it allowed for more c…

Grout Drawings Notes Confusion

STATEMENT OF PROBLEM Notes for grout at rails etc. do not reflect as installed. Grout notes on drawings create confusion for installation contractors. It drives cost into the quote and wasted time in clarifications and instruction. COURSE OF ACTION None LESSON LEARNED AE to work more closely with Press Engin…

Press bay turnover checklist and sign-off sheet

STATEMENT OF PROBLEM A checklist was not used to facilitate the turnover of the press bay from Facilities to the Press group. Caused some discussions to be missed. COURSE OF ACTION None LESSON LEARNED Institute the buy-off checklist with meeting on ALL press projects.

Incorrectly Cored Tie Rod Pockets

STATEMENT OF PROBLEM Two tie rod pockets were cored in the wrong location. One dimension provided by the Press Group was transposed incorrectly, which migrated into the contract documents. The holes were cored per the drawings. The discrepancy was not discovered until press install, which caused some schedule del…

As Built Conditions Expectation Issue

STATEMENT OF PROBLEM Need clear expectations of what items are existing. What is to remain, or be removed. Confusion to bidders; cost increase due to field orders. COURSE OF ACTION None LESSON LEARNED Work more closely with AE''''''''s to capture as-built conditions at project completion, and to verify condi…

scroll to top icon