GC Direct Procurement of Doors/Frames/Hardware
Project: StarPlus Energy Battery Plant CCC Job#3374 STATEMENT OF PROBLEM: Owner attempted to save money by purchasing DFH through the GC instead of installing contractor. ROOT CAUSE: COURSE OF ACTION: The GC project manager held weekly coordination meetings with the installers and vendor to discuss and so…
-
Roll Up Door Requirements
STATEMENT OF PROBLEM No direct discussion with material handling group led to incorrect door equipment being spec''''''''d. Increased cost due to field order; unhappy customer. COURSE OF ACTION Field order (cost and schedule impact) LESSON LEARNED Better communication with the right parties at…