Project: StarPlus Energy Battery Plant CCC Job#3374 STATEMENT OF PROBLEM: Owner attempted to save money by purchasing DFH through the GC instead of installing contractor. ROOT CAUSE: COURSE OF ACTION: The GC project manager held weekly coordination meetings with the installers and vendor to discuss and so…

Roll Up Door Requirements

STATEMENT OF PROBLEM No direct discussion with material handling group led to incorrect door equipment being spec''''''''d. Increased cost due to field order; unhappy customer. COURSE OF ACTION Field order (cost and schedule impact) LESSON LEARNED Better communication with the right parties at…