STATEMENT OF PROBLEM Not sure what the objective is for uploading WIM every couple weeks. Other GM groups constantly were working off old models or didn’t know where to even download this info. Many times when they finally downloaded model, work has already taken place in field and then the Process groups has is…
STATEMENT OF PROBLEM Late addition of owner''''s alternates; Inadequate drawings and write-ups. Unclear to bidders; disparity in costs, or non representative cost. COURSE OF ACTION None LESSON LEARNED Need more clear definition in the drawings and scope write-up.
STATEMENT OF PROBLEM Plant preference was piped eyewash station; RE&F position to use portable system. Is cost savings justifiable? Unhappy customer; safety/maintenance? COURSE OF ACTION Provided portable eyewash station LESSON LEARNED Continue to provide the portable eyewash stations to align…
STATEMENT OF PROBLEM Provided a high level of detail of the existing framing and utility conditions that would not be clear on the as-built drawings. Highlighted areas where framing and utilities could go without impacting process equipment. Reduced engineering time and field interference. COURSE OF ACTION …
STATEMENT OF PROBLEM Having and onsite Engineering Representative may deem cost effective for projects of substantial size and duration. This Rep should be able to make PM decisions from and engineering standpoint and be fluid with model integration, review and document control changes. For project requiring 3D …
STATEMENT OF PROBLEM Should have been coordinated with "Owner" prior to issuing bid drawings; Lazy approach by team to just "copy"; Information was known, and could have been committed to. Many DCRs; schedule delays; cost increase due to field orders COURSE OF ACTION Field orders (schedule delays, cost …
STATEMENT OF PROBLEM Need clear expectations of what items are existing. What is to remain, or be removed. Confusion to bidders; cost increase due to field orders. COURSE OF ACTION None LESSON LEARNED Work more closely with AE''''''''s to capture as-built conditions at project completion, and to verify condi…
STATEMENT OF PROBLEM Problem was identifying all stakeholders at beginning of project. Problems or input was sometimes too late, and was delivered to project team after starting construction. Some cases issues were brought up after construction completion by an unnamed party. Other problem is the GM Reviews onl…
STATEMENT OF PROBLEM No direct discussion with material handling group led to incorrect door equipment being spec''''''''d. Increased cost due to field order; unhappy customer. COURSE OF ACTION Field order (cost and schedule impact) LESSON LEARNED Better communication with the right parties at…
STATEMENT OF PROBLEM Interference between cross bar support pockets and structural steel. Additional cost and delays due to field rework required to make the crossbar pocket fit. COURSE OF ACTION None LESSON LEARNED review engineering & revise drawings