STATEMENT OF PROBLEM Problem was identifying all stakeholders at beginning of project. Problems or input was sometimes too late, and was delivered to project team after starting construction. Some cases issues were brought up after construction completion by an unnamed party. Other problem is the GM Reviews onl…
STATEMENT OF PROBLEM Deviation from the designed guardrail. Missing connection pieces, incorrect member sizes, incorrect height, not submitted in shop drawings. Created potentially unsafe condition; additional time to correct; non-conformance to customer''''''''s requirements. COURSE OF ACTION Repaired …
STATEMENT OF PROBLEM Civil Design/Build is usually based on existing top surveys and existing Civil drawings. These are never accurate as far as dimensions go (most cases). Although the routing is sometimes close the act of integrating a new Model design with archival u/g drawings to reduce clashes is arbitrary and…
STATEMENT OF PROBLEM Shared construction space between facility contractor and press installation contractor. Safety concerns; schedule delay. COURSE OF ACTION None LESSON LEARNED Better understanding of what was coming in and when. CCC worked very well with IICC in coordinating the space.
STATEMENT OF PROBLEM The modification of the existing Sub 4A switchgear to accommodate a new 2000A feed was separated out of the main contract in an effort to reuse available assets and perform work during the 2011 X-mas shutdown. The original timeframe could not be allowed by the plant. Solaris documentation and…
STATEMENT OF PROBLEM Multiple instances where existing framing to remain was cut due to incorrect depth set on saw; damaged the integrity, and reduced the capacity of the existing members. Schedule impact for repair; additional engineering; non-standard condition for owner. COURSE OF ACTION Repaired (schedule im…
STATEMENT OF PROBLEM Not enough direct communication with the plant personnel during design decisions. Lack of understanding of substation work; incorrect door specified; confusion on partition walls and take shelter routes; eyewash station dispute; COURSE OF ACTION None LESSON LEARNED RE&F Co…
STATEMENT OF PROBLEM Tie rod pockets are not included in basement floor layout. Tie rods extend above columns when setting crown. All 10 tie rods have to be guided by hand into the crown. SAFETY -personel must now be working above ground & under crown when it is being lowered. DAMAGE increased risk to tie rod thr…
STATEMENT OF PROBLEM AE response time on submittals and DCRs not meeting expectation of contractor. Delays and schedule impacts; friction between parties. COURSE OF ACTION None LESSON LEARNED There were some issues during the early steel submitting, but after that the process went smoothly.
STATEMENT OF PROBLEM Drawings lack as installed detail regarding floor support at the cam box. lack of detail drives cost in additional material, work, and direction. COURSE OF ACTION None LESSON LEARNED Work with Press Engineers to gather detailed drawings of field fixes from previous install…