STATEMENT OF PROBLEM Having and onsite Engineering Representative may deem cost effective for projects of substantial size and duration. This Rep should be able to make PM decisions from and engineering standpoint and be fluid with model integration, review and document control changes. For project requiring 3D …
STATEMENT OF PROBLEM Many instances the as-built buildings the a new building addition ties into are not square, plumb, or columns may not be accurately spaced. Some instances roof line is also uneven. CCC did not perform all facets of conducting a "Thorough" Existing Building Survey. We spaced our columns on a g…
STATEMENT OF PROBLEM Not enough direct communication with the plant personnel during design decisions. Lack of understanding of substation work; incorrect door specified; confusion on partition walls and take shelter routes; eyewash station dispute; COURSE OF ACTION None LESSON LEARNED RE&F Co…
STATEMENT OF PROBLEM Need clear expectations of what items are existing. What is to remain, or be removed. Confusion to bidders; cost increase due to field orders. COURSE OF ACTION None LESSON LEARNED Work more closely with AE''''''''s to capture as-built conditions at project completion, and to verify condi…
STATEMENT OF PROBLEM Deviation from the designed guardrail. Missing connection pieces, incorrect member sizes, incorrect height, not submitted in shop drawings. Created potentially unsafe condition; additional time to correct; non-conformance to customer''''''''s requirements. COURSE OF ACTION Repaired …
STATEMENT OF PROBLEM The modification of the existing Sub 4A switchgear to accommodate a new 2000A feed was separated out of the main contract in an effort to reuse available assets and perform work during the 2011 X-mas shutdown. The original timeframe could not be allowed by the plant. Solaris documentation and…
STATEMENT OF PROBLEM Additional floor support is required to support the elec. platform. schedule delay as elec platform cannot be installed until floor is poured. COURSE OF ACTION Poured floor before installing platform (schedule delay). LESSON LEARNED Capture Pontiac AA0 solution and incorporate into drawi…
STATEMENT OF PROBLEM Multiple instances where existing framing to remain was cut due to incorrect depth set on saw; damaged the integrity, and reduced the capacity of the existing members. Schedule impact for repair; additional engineering; non-standard condition for owner. COURSE OF ACTION Repaired (schedule im…
STATEMENT OF PROBLEM Sometimes we lack detailed information for scrap conveyor system (i.e. routing, sizes, clearances, etc.). Multiple iterations of engineering. COURSE OF ACTION None LESSON LEARNED Great upfront support. AE was provided with a scrap conveyor route and 3D model in the beginni…
STATEMENT OF PROBLEM Too tight/unrealistic to begin with; Should work with Press group as early as possible to meet agrreement; Contractor disagreed with tolerances although they were part of the contractor documents, no bid clarification question. Potential concern for fabrication and setting tolerances; meeting…