STATEMENT OF PROBLEM The modification of the existing Sub 4A switchgear to accommodate a new 2000A feed was separated out of the main contract in an effort to reuse available assets and perform work during the 2011 X-mas shutdown. The original timeframe could not be allowed by the plant. Solaris documentation and…
Project Phase- Construction/Installation Delivery Method- General Contract-Prime Base Contract schedule was very aggressive, with tooling being installed while demo activities were taking place. This schedule was in the bid documents and we agreed to it. The central area being demolished was isolated within th…