Job #3007 Ford Chicago Assembly - Demolition STATEMENT OF PROBLEM The plant was extremely loud during the demolition which made it difficult to communicate via cell phone. ROOT CAUSE Did not plan for how team would effectively communicate amongst high noise levels. COURSE OF ACTION No course o…
Project Phase- Construction/Installation Delivery Method- General Contract-Prime Base Contract schedule was very aggressive, with tooling being installed while demo activities were taking place. This schedule was in the bid documents and we agreed to it. The central area being demolished was isolated within th…