STATEMENT OF PROBLEM: CCC was tasked to remove a slab on metal deck (SOMD) on the first floor of the hospital for installation of new structural steel to provide a stronger SOMD for the MRI machine to be installed. CCC marked the slab removal per the drawings and had the SOMD shored from below with 2 additi…
Project Phase - Construction/Installation Delivery Method- General Contract-Prime After demolition completion, the owner came back and stated that CCC had damaged some things, and we had no way of knowing who broke it / prove them wrong.
Project Phase- Construction/Installation Delivery Method- General Contract-Prime As part of the scope we were to identify and mark utilities to be air gapped for make safe demolition. The routing of these utilities, plant logistics and infrastructure in place made the identification and marking of these uti…
Project Phase- Construction/Installation Delivery Method- General Contract-Prime Schedule Delay- Adamo fell behind during demolition of existing tooling in the Body Shop for several reasons. Inexperienced workforce was the biggest contributing factor along with union problems. Not only was the union unwilling to …
Project Phase- Construction/Installation Delivery Method- General Contract-Prime Base Contract schedule was very aggressive, with tooling being installed while demo activities were taking place. This schedule was in the bid documents and we agreed to it. The central area being demolished was isolated within th…
STATEMENT OF PROBLEM: There was areas on the first floor where new utilities needed to be ran. The drawings showed new lines being ran but did not show that the existing hard lid ceiling needed to be removed in order for the mechanical contractor to do their work. It may have been assumed that the mechanical crew cou…