Project Phase- Design Delivery Method- General Contract-Prime The plant was dark and due to the work activity we needed to constantly point things out in the truss space and did not have a means to do this.
Job #3007 Ford Chicago Assembly - Demolition STATEMENT OF PROBLEM The plant was extremely loud during the demolition which made it difficult to communicate via cell phone. ROOT CAUSE Did not plan for how team would effectively communicate amongst high noise levels. COURSE OF ACTION No course o…
Project Phase: Estimating Delivery Method: Construction Mgmt. Communication between shifts, there was no follow through on second shift. Plans provided.