STATEMENT OF PROBLEM Need clear expectations of what items are existing. What is to remain, or be removed. Confusion to bidders; cost increase due to field orders. COURSE OF ACTION None LESSON LEARNED Work more closely with AE''''''''s to capture as-built conditions at project completion, and to verify condi…
STATEMENT OF PROBLEM Disconnect between RE&F intent and what was stated on drawings. Increased cost of purchasing new bus duct. COURSE OF ACTION Purchased new bus duct (increased cost). LESSON LEARNED Work with AE to develop more clear expectations for reuse.
STATEMENT OF PROBLEM Many instances the as-built buildings the a new building addition ties into are not square, plumb, or columns may not be accurately spaced. Some instances roof line is also uneven. CCC did not perform all facets of conducting a "Thorough" Existing Building Survey. We spaced our columns on a g…
STATEMENT OF PROBLEM Notes for grout at rails etc. do not reflect as installed. Grout notes on drawings create confusion for installation contractors. It drives cost into the quote and wasted time in clarifications and instruction. COURSE OF ACTION None LESSON LEARNED AE to work more closely with Press Engin…
STATEMENT OF PROBLEM Ambiguity created between drawings, owner''''s intent, and contractor''''s understanding. The Ghafari drawings create some confusion between a general note on the plan vs. the intent on the details. As a result, neither the facility contractor or the press contractor included the erection of …
STATEMENT OF PROBLEM All of the above factors did not export the best and most efficient design for the new 354 roof to tie into the existing 384 roof. Existing slopes and drains were not engineered with actual site conditions taken into account. This type of situation is not easily noticed on paper or in a DIM …
STATEMENT OF PROBLEM Lacking detailed information for routing (i.e. elevations, dimensions, sections, etc.). Contractor claimed responsibility for system locations, which were already coordinated in 3D environment. COURSE OF ACTION None LESSON LEARNED Work with AE to develop a common understanding of expecta…
STATEMENT OF PROBLEM Broom finish allows oil buildup. Build up of oils create long term house keeping and safety issues. COURSE OF ACTION None LESSON LEARNED Use trowel finish as standard. Discuss with plants on a project by project basis.
STATEMENT OF PROBLEM Too tight/unrealistic to begin with; Should work with Press group as early as possible to meet agrreement; Contractor disagreed with tolerances although they were part of the contractor documents, no bid clarification question. Potential concern for fabrication and setting tolerances; meeting…
STATEMENT OF PROBLEM AE response time on submittals and DCRs not meeting expectation of contractor. Delays and schedule impacts; friction between parties. COURSE OF ACTION None LESSON LEARNED There were some issues during the early steel submitting, but after that the process went smoothly.