STATEMENT OF PROBLEM Ambiguity created between drawings, owner''''s intent, and contractor''''s understanding. The Ghafari drawings create some confusion between a general note on the plan vs. the intent on the details. As a result, neither the facility contractor or the press contractor included the erection of …
STATEMENT OF PROBLEM: CCC bid a project and provided an overall deduct from the base bid for the value of the scrap. The value of scrap was based on a quoted market value of approximately 450 USD per gross ton. As the project progressed, the market value of scrap steel dropped to approximately 200 USD a gross ton…