As Built Conditions Expectation Issue
STATEMENT OF PROBLEM Need clear expectations of what items are existing. What is to remain, or be removed. Confusion to bidders; cost increase due to field orders. COURSE OF ACTION None LESSON LEARNED Work more closely with AE''''''''s to capture as-built conditions at project completion, and to verify condi…
-
Submittal/DCR Response Time
STATEMENT OF PROBLEM AE response time on submittals and DCRs not meeting expectation of contractor. Delays and schedule impacts; friction between parties. COURSE OF ACTION None LESSON LEARNED There were some issues during the early steel submitting, but after that the process went smoothly.
-
Fairfax Subcontractor 3D Model Training
STATEMENT OF PROBLEM Many Subcontractors are not familiar with 3D Model design and/or design build. The limited pool of contractors who can bid GM work due to NMA and Safety Guidelines is very limited. Problem is learning curve to train subcontractors to build per model without the proverbial "shoving the require…