JOB #3346 Michigan Gas utility- Jackson STATEMENT OF PROBLEM: A compressor pad was erected and the compressor later installed. Cementitious grout was carried in the estimate, however the line item on our proposal indicated (furnish and provide grout at compressor pad". This application required epoxy grout and w…
STATEMENT OF PROBLEM Notes for grout at rails etc. do not reflect as installed. Grout notes on drawings create confusion for installation contractors. It drives cost into the quote and wasted time in clarifications and instruction. COURSE OF ACTION None LESSON LEARNED AE to work more closely with Press Engin…