Site Logistics and Temporary Access

STATEMENT OF PROBLEM: During the pre-construction phase of the Delta Township WRRF, the provision and installation of temporary haul roads was unfortunately overlooked. The result of unforeseen costs associated with building these temporary haul roads required large portions of the budget allowance to be used. In ad…

Roof Maintenance Access

Project Phase: Construction Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: During the design phase of the BP-06 architectural build out, the height of the mezzanine in relation of the roof steel and height of the low roof did not allow for the chain hoist/rail within the high ba…