You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from FCA tag

SSP Stripping Dock Engineering Issues

STATEMENT OF PROBLEM Both sets of drawings were submitted, reviewed, and approved by CCC and Chrysler. CCC Trades laid out the installed the pits per the Gala drawings. When we set the dock levelers, they sat above the finished floor. The leveler pit bottom was 4" too high. COURSE OF ACTION Demo and rep…

WTAP MOVE Finesse Deck - Verify Existing Building Steel Conditions

STATEMENT OF PROBLEM: Column line Abe, as shown on the print (Trans 23, 948-0170-700-709), is not shown in the correct place on the floor. The print shows (45-0 + 4-0) 49''-0", but it physically measures about 53''-3". (4''-3" discrepancy) The install team started install from the East and worked to the W…

Existing Building Steel Plumbness

STATEMENT OF PROBLEM: One of the main portions of work that we were tasked to complete was building a 120,000 square foot addition that directly tied into the existing plant. Unbeknownst to the project team at bid time, the existing building columns were out of plumb and leaning away from the addition. The first row …

Limestone Sand Subbase

STATEMENT OF PROBLEM: Even after compaction of limestone sand, the concrete trucks would create ruts while crossing the grade. Extra grading would be needed as concrete was being placed to reduce this rutting. COURSE OF ACTION: The limestone sand was replaced with crushed limestone where feasible to provide a m…

Crane Mat

STATEMENT OF PROBLEM: For the structural steel portion of this project, a Manitowoc 555 was brought in to erect the building. The 3 issues we ran across were that we needed a suitable crane mat, we needed to grade out the site, and we needed to complete numerous underground storm repairs, (most were not designed yet)…

Tie-in to Existing Building/Patching

STATEMENT OF PROBLEM: There were several penetrations in various locations that required cutting/coring, weatherproofing, patching, etc. that our subcontractors had excluded in their original estimates. The cutting and patching involved with these tie-ins not specifically shown on the drawings, and was not covered in…

Structural Steel Prime/Paint

STATEMENT OF PROBLEM: The condition of the erected and finished white structural steel was deemed unacceptable by FCA/CCC. During pre-bid discussions, it was determined that white paint from Prospect''''s fab shop could pass as finish paint. Schedule delays and seasonal conditions caused wear and tear on the SP3 stee…

scroll to top icon