Project Phase: Construction Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: Precast plank installation over toilet rooms, within building after steel was erected. Based on the lead time of the precast the lid had to be installed after the roof steel was erected and there was …
STATEMENT OF PROBLEM: For the structural steel portion of this project, a Manitowoc 555 was brought in to erect the building. The 3 issues we ran across were that we needed a suitable crane mat, we needed to grade out the site, and we needed to complete numerous underground storm repairs, (most were not designed yet)…