Showing articles from structural steel tag

Crane Mat

STATEMENT OF PROBLEM: For the structural steel portion of this project, a Manitowoc 555 was brought in to erect the building. The 3 issues we ran across were that we needed a suitable crane mat, we needed to grade out the site, and we needed to complete numerous underground storm repairs, (most were not designed yet)…

Structural Steel Prime/Paint

STATEMENT OF PROBLEM: The condition of the erected and finished white structural steel was deemed unacceptable by FCA/CCC. During pre-bid discussions, it was determined that white paint from Prospect''''s fab shop could pass as finish paint. Schedule delays and seasonal conditions caused wear and tear on the SP3 stee…