Floor Patching

Project Phase- Design Delivery Method- General Contract-Prime There was a T&M allowance for floor patching. A week before job start, Owner notified CCC we would be doing the patching. Floor patching material wasn''t approved until a few days prior to the start of shutdown. The material wasn''t going to …

Tie-in to Existing Building/Patching

STATEMENT OF PROBLEM: There were several penetrations in various locations that required cutting/coring, weatherproofing, patching, etc. that our subcontractors had excluded in their original estimates. The cutting and patching involved with these tie-ins not specifically shown on the drawings, and was not covered in…