STATEMENT OF PROBLEM Both sets of drawings were submitted, reviewed, and approved by CCC and Chrysler. CCC Trades laid out the installed the pits per the Gala drawings. When we set the dock levelers, they sat above the finished floor. The leveler pit bottom was 4" too high. COURSE OF ACTION Demo and rep…
Project Phase: Estimating Delivery Method: General Contract-Sub Estimating made the assumption that VDLs were shipped in and never ran off. CCC doubled hours due to this. Manual provided for installation was not used per VDL Expert.