You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from GM tag

GM Pontiac Toilet Room Basin Sinks

STATEMENT OF PROBLEM Incorrectly sized basin-style sinks were installed in the mens and womens toilet rooms, which created a code violation where the egress minimum width of 36" was impeded in the mens toilet room entrance way. The architect sized and placed the basin-style sinks at mens and womens locker rooms but …

AE Submittal Return Process & Submittal Review

STATEMENT OF PROBLEM Throughout the job there were critical submittals CCC needed prompt reply on in order to complete work per the schedule. Submittals that were delayed (in this case most notably structural steel submittals) caused schedule delays for CCC in ordering materials/completing the work. While many su…

GM Pontiac Tooling Cart Trenches Dimensional Error

STATEMENT OF PROBLEM During the revisions being made to the Rotem drawings, on revision 5 Rotem changed the width and depth for one of the two tooling cart rails for each tooling cart rail system located between the presses (4 sets of rails total). The trench for the rail became wider by several millimeters and deep…

GM Pontiac Process (Press) Design Drawings coordination with Facility drawings

STATEMENT OF PROBLEM There were several issues to where the 2D press drawings provided by Rotem did not show enough detailed information for proper coordination. These included: 1) the press cable trays in pit  2) The platforms and ladders between the presses. 3) D/B team not having a useable press 3D…

GM Pontiac Cooling Tower System Design

STATEMENT OF PROBLEM Before the cooling tower system was turned over to the plant, an oily sheen was discovered in the basins by GM. CCC mitigated the issue with oil socks but it was brought up by the plant on why the filter was not running/filtering the oil. This was because the filter is not meant to filter oil…

GM Pontiac A-line Existing Foundations

STATEMENT OF PROBLEM At bid time CCC received the 1950 Albert Kahn facility record drawings of the plant. This set had two foundation drawings, showing two different column foundation types for the plant. One drawing showed all footings, one drawing showed all caissons. It was unknown by GM which was the as-built…

Estimating and VDL Knowledge

Project Phase: Estimating Delivery Method: General Contract-Sub Estimating made the assumption that VDLs were shipped in and never ran off. CCC doubled hours due to this. Manual provided for installation was not used per VDL Expert.

GM Pontiac Process Utility Holes Over Press Pit

STATEMENT OF PROBLEM Once the press pit steel design was complete, CCC provided the pit framing steel model / 2D drawings to GM to provide to Rotem for their use. Rotem placed approximately 45 openings through the rebar SOD, and provided the 2D process drawing to GM/CCC. This drawing underwent 10 revisions by Rot…

GM Pontiac Establishing an Elevation of Top of Floor - Impact on Process

STATEMENT OF PROBLEM During design, elevations were taken along the existing A-line floor and along the MPS building. These elevations were used to average a finish floor level for the building addition. In original design, two die cart rails ran N-S from the die wash booth to A1-line. However after the construct…

New Cooling Tower Mechanical/Structural Coordination

Statement of Problem: In the design coordination of the cooling tower cells and the steel support platform, there was a disconnect in the 3D model between JEG and IBI with the actual elevation of the cells. Additionally, JEG changed the piping configuration to the basins and this impact was not discussed with the…

scroll to top icon