Field Checks not being completed
Project Phase: Installation Delivery Method: General Contract-Sub Customer and Prime field checks were not complete and / or not accurate.
-
Piping Subcontractor Steel
STATEMENT OF PROBLEM: This project had a substantial amount of header steel required for the coolant supply and return mains. Since this header steel was only to support the piping, the steel was awarded to the piping subcontractor and they were responsible for design and install. The piping subcontractor submitted …
-
Document Control Lacked by Prime
Project Phase: Procedural Management Delivery Method: General Contractor-Sub Document control lacked by Prime. Data storage, drawing log, punch list, etc....was not available.