You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from GM tag

Datum Points Not Correctly Coordinated

8575 GM Ultium 2 Battery Plant STATEMENT OF PROBLEM 1. Bass Datums were not coordinated correctly/accurately. In turn, system integration was challenging. 2. Avaco did not have the skilled help they needed on site. 3. The schedule was built to construct all of Pancake Line-3, and then, all of Pancake NnD Input …

GM Pontiac Tooling Cart Trenches Dimensional Error

STATEMENT OF PROBLEM During the revisions being made to the Rotem drawings, on revision 5 Rotem changed the width and depth for one of the two tooling cart rails for each tooling cart rail system located between the presses (4 sets of rails total). The trench for the rail became wider by several millimeters and deep…

Unknown As-Built Conditions

Statement of Problem: At bid time CCC received the 1950 Albert Kahn facility record drawings of the plant. This set had two foundation drawings, showing two different column foundation types for the plant. One drawing showed all footings, one drawing showed all caissons. It was unknown by GM which was the as-built c…

GM Pontiac Substation W Equipment Floor Loading Issue

STATEMENT OF PROBLEM CCC received the substation equipment shop drawings from GM late in the project, at end of July. In August CCC worked with GM on the rigging plan for hoisting the new substation equipment into the penthouse. IBI performed a structural analysis of the penthouse framing steel and the hoist beam…

Coordination of Mechanical Equipment & Site Structural Support Pads

STATEMENT OF PROBLEM: A coordination meeting between structural/civil/mechanical was held for the outdoor air rotation units which sit on concrete pads. In the meeting JEG gave the required dimensions of the pad and stated the ARU & pad should be centered within the building column bay. The pads were then designed b…

GM Pontiac Process (Press) Design Drawings coordination with Facility drawings

STATEMENT OF PROBLEM There were several issues to where the 2D press drawings provided by Rotem did not show enough detailed information for proper coordination. These included: 1) the press cable trays in pit  2) The platforms and ladders between the presses. 3) D/B team not having a useable press 3D…

GM Arlington Assembly Non-Conforming Work Poor Concrete Finish

STATEMENT OF PROBLEM Poor finish on exterior concrete. Exterior concrete batch error. There was clumping or balling of synthetic fibers on the interior slab. Post project review shows poor grading and compaction of sub-grade and excessive fibers protruding from the slab. COURSE OF ACTION Offered GM an e…

GM Pontiac Toilet Room Basin Sinks

STATEMENT OF PROBLEM Incorrectly sized basin-style sinks were installed in the mens and womens toilet rooms, which created a code violation where the egress minimum width of 36" was impeded in the mens toilet room entrance way. The architect sized and placed the basin-style sinks at mens and womens locker rooms but …

Inefficiencies and lost time due to lack of bolt bin

Project Phase: Project Delivery Method: General Contract-Sub No mobile bolt bin created field inefficiencies and lost time.

GM Pontiac Fire Alarm Design Review

STATEMENT OF PROBLEM The electrical subcontractor contracted Siemens to perform the fire alarm design. The drawings were submtited and reviewed by IBI and were also reviewed and approved by the city/fire department. However it was identified after the fact that the fire alarm drawings did not include smoke detect…

scroll to top icon