You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from Fairfax tag

EOL Elec Platform Beam Supports

STATEMENT OF PROBLEM Additional floor support is required to support the elec. platform. schedule delay as elec platform cannot be installed until floor is poured. COURSE OF ACTION Poured floor before installing platform (schedule delay). LESSON LEARNED Capture Pontiac AA0 solution and incorporate into drawi…

Fairfax Owners Alternatives Communication

STATEMENT OF PROBLEM Late addition of owner''''s alternates; Inadequate drawings and write-ups. Unclear to bidders; disparity in costs, or non representative cost. COURSE OF ACTION None LESSON LEARNED Need more clear definition in the drawings and scope write-up.

Grout Drawings Notes Confusion

STATEMENT OF PROBLEM Notes for grout at rails etc. do not reflect as installed. Grout notes on drawings create confusion for installation contractors. It drives cost into the quote and wasted time in clarifications and instruction. COURSE OF ACTION None LESSON LEARNED AE to work more closely with Press Engin…

As Built Conditions Expectation Issue

STATEMENT OF PROBLEM Need clear expectations of what items are existing. What is to remain, or be removed. Confusion to bidders; cost increase due to field orders. COURSE OF ACTION None LESSON LEARNED Work more closely with AE''''''''s to capture as-built conditions at project completion, and to verify condi…

Remote Jobsite Design/Management Techniques

STATEMENT OF PROBLEM Problem was identifying all stakeholders at beginning of project.  Problems or input was sometimes too late, and was delivered to project team after starting construction. Some cases issues were brought up after construction completion by an unnamed party.  Other problem is the GM Reviews onl…

Eyewash Station System Cost Savings

STATEMENT OF PROBLEM Plant preference was piped eyewash station; RE&F position to use portable system. Is cost savings justifiable? Unhappy customer; safety/maintenance? COURSE OF ACTION Provided portable eyewash station LESSON LEARNED Continue to provide the portable eyewash stations to align…

Fairfax Incorrect Guardrail Installation

STATEMENT OF PROBLEM Deviation from the designed guardrail. Missing connection pieces, incorrect member sizes, incorrect height, not submitted in shop drawings. Created potentially unsafe condition; additional time to correct; non-conformance to customer''''''''s requirements. COURSE OF ACTION Repaired …

2D Vs. 3D Deliverable

STATEMENT OF PROBLEM Should the design been issued as a 3D deliverable, or was the 2D deliverable with 3D coordination model adequate? Disconnect between what was coordinated in the 3D model, the actual 2D contract documents, and what was constructed. COURSE OF ACTION Require 3D design LESSON LEAR…

Crossbar Support Pockets Issue

STATEMENT OF PROBLEM Interference between cross bar support pockets and structural steel. Additional cost and delays due to field rework required to make the crossbar pocket fit.  COURSE OF ACTION None LESSON LEARNED review engineering & revise drawings

Fairfax Substation Modification Time Frame Issues

STATEMENT OF PROBLEM The modification of the existing Sub 4A switchgear to accommodate a new 2000A feed was separated out of the main contract in an effort to reuse available assets and perform work during the 2011 X-mas shutdown. The original timeframe could not be allowed by the plant. Solaris documentation and…

scroll to top icon