STATEMENT OF PROBLEM Additional floor support is required to support the elec. platform. schedule delay as elec platform cannot be installed until floor is poured. COURSE OF ACTION Poured floor before installing platform (schedule delay). LESSON LEARNED Capture Pontiac AA0 solution and incorporate into drawi…
STATEMENT OF PROBLEM Deviation from the designed guardrail. Missing connection pieces, incorrect member sizes, incorrect height, not submitted in shop drawings. Created potentially unsafe condition; additional time to correct; non-conformance to customer''''''''s requirements. COURSE OF ACTION Repaired …
STATEMENT OF PROBLEM Late addition of owner''''s alternates; Inadequate drawings and write-ups. Unclear to bidders; disparity in costs, or non representative cost. COURSE OF ACTION None LESSON LEARNED Need more clear definition in the drawings and scope write-up.
STATEMENT OF PROBLEM Notes for grout at rails etc. do not reflect as installed. Grout notes on drawings create confusion for installation contractors. It drives cost into the quote and wasted time in clarifications and instruction. COURSE OF ACTION None LESSON LEARNED AE to work more closely with Press Engin…
STATEMENT OF PROBLEM Should have been coordinated with "Owner" prior to issuing bid drawings; Lazy approach by team to just "copy"; Information was known, and could have been committed to. Many DCRs; schedule delays; cost increase due to field orders COURSE OF ACTION Field orders (schedule delays, cost …
STATEMENT OF PROBLEM Multiple instances where existing framing to remain was cut due to incorrect depth set on saw; damaged the integrity, and reduced the capacity of the existing members. Schedule impact for repair; additional engineering; non-standard condition for owner. COURSE OF ACTION Repaired (schedule im…
STATEMENT OF PROBLEM Not enough direct communication with the plant personnel during design decisions. Lack of understanding of substation work; incorrect door specified; confusion on partition walls and take shelter routes; eyewash station dispute; COURSE OF ACTION None LESSON LEARNED RE&F Co…
STATEMENT OF PROBLEM The modification of the existing Sub 4A switchgear to accommodate a new 2000A feed was separated out of the main contract in an effort to reuse available assets and perform work during the 2011 X-mas shutdown. The original timeframe could not be allowed by the plant. Solaris documentation and…
STATEMENT OF PROBLEM Tie rod pockets are not included in basement floor layout. Tie rods extend above columns when setting crown. All 10 tie rods have to be guided by hand into the crown. SAFETY -personel must now be working above ground & under crown when it is being lowered. DAMAGE increased risk to tie rod thr…
STATEMENT OF PROBLEM Should the design been issued as a 3D deliverable, or was the 2D deliverable with 3D coordination model adequate? Disconnect between what was coordinated in the 3D model, the actual 2D contract documents, and what was constructed. COURSE OF ACTION Require 3D design LESSON LEAR…