You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from Fairfax tag

On Site EOR Representation for Projects of Significant Scale/Cost

STATEMENT OF PROBLEM Having and onsite Engineering Representative may deem cost effective for projects of substantial size and duration.  This Rep should be able to make PM decisions from and engineering standpoint and be fluid with model integration, review and document control changes. For project requiring 3D …

EOL Elec Platform Beam Supports

STATEMENT OF PROBLEM Additional floor support is required to support the elec. platform. schedule delay as elec platform cannot be installed until floor is poured. COURSE OF ACTION Poured floor before installing platform (schedule delay). LESSON LEARNED Capture Pontiac AA0 solution and incorporate into drawi…

Fairfax Incorrect Guardrail Installation

STATEMENT OF PROBLEM Deviation from the designed guardrail. Missing connection pieces, incorrect member sizes, incorrect height, not submitted in shop drawings. Created potentially unsafe condition; additional time to correct; non-conformance to customer''''''''s requirements. COURSE OF ACTION Repaired …

Roll Up Door Requirements

STATEMENT OF PROBLEM No direct discussion with material handling group led to incorrect door equipment being spec''''''''d. Increased cost due to field order; unhappy customer. COURSE OF ACTION Field order (cost and schedule impact) LESSON LEARNED Better communication with the right parties at…

Remote Jobsite Design/Management Techniques

STATEMENT OF PROBLEM Problem was identifying all stakeholders at beginning of project.  Problems or input was sometimes too late, and was delivered to project team after starting construction. Some cases issues were brought up after construction completion by an unnamed party.  Other problem is the GM Reviews onl…

Bus Duct Reuse

STATEMENT OF PROBLEM Disconnect between RE&F intent and what was stated on drawings. Increased cost of purchasing new bus duct. COURSE OF ACTION Purchased new bus duct (increased cost). LESSON LEARNED Work with AE to develop more clear expectations for reuse.

2D Vs. 3D Deliverable

STATEMENT OF PROBLEM Should the design been issued as a 3D deliverable, or was the 2D deliverable with 3D coordination model adequate? Disconnect between what was coordinated in the 3D model, the actual 2D contract documents, and what was constructed. COURSE OF ACTION Require 3D design LESSON LEAR…

Fairfax Substation Modification Time Frame Issues

STATEMENT OF PROBLEM The modification of the existing Sub 4A switchgear to accommodate a new 2000A feed was separated out of the main contract in an effort to reuse available assets and perform work during the 2011 X-mas shutdown. The original timeframe could not be allowed by the plant. Solaris documentation and…

Grout Drawings Notes Confusion

STATEMENT OF PROBLEM Notes for grout at rails etc. do not reflect as installed. Grout notes on drawings create confusion for installation contractors. It drives cost into the quote and wasted time in clarifications and instruction. COURSE OF ACTION None LESSON LEARNED AE to work more closely with Press Engin…

Tie Rod Pockets

STATEMENT OF PROBLEM Tie rod pockets are not included in basement floor layout. Tie rods extend above columns when setting crown. All 10 tie rods have to be guided by hand into the crown. SAFETY -personel must now be working above ground & under crown when it is being lowered. DAMAGE increased risk to tie rod thr…

scroll to top icon