You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from AA3X tag

Middle Bay Press Compressed Air Criteria Issue

STATEMENT OF PROBLEM The compressed air demand for the two presses and FOL equipment changed after the contract aware. This was in part due to a new system late that was still being worked out in Fairfax, and all of the necessary testing was not complete prior to award. Extra effort for engineering to run through…

Scrap Conveyor System Information Issue

STATEMENT OF PROBLEM Sometimes we lack detailed information for scrap conveyor system (i.e. routing, sizes, clearances, etc.). Multiple iterations of engineering. COURSE OF ACTION None LESSON LEARNED Great upfront support. AE was provided with a scrap conveyor route and 3D model in the beginni…

Broom Finish Bolster Area Oil Buildup

STATEMENT OF PROBLEM Broom finish allows oil buildup. Build up of oils create long term house keeping and safety issues. COURSE OF ACTION None LESSON LEARNED Use trowel finish as standard. Discuss with plants on a project by project basis.

Roll Up Door Requirements

STATEMENT OF PROBLEM No direct discussion with material handling group led to incorrect door equipment being spec''''''''d. Increased cost due to field order; unhappy customer. COURSE OF ACTION Field order (cost and schedule impact) LESSON LEARNED Better communication with the right parties at…

Sawcutting Quality Control

STATEMENT OF PROBLEM Multiple instances where existing framing to remain was cut due to incorrect depth set on saw; damaged the integrity, and reduced the capacity of the existing members. Schedule impact for repair; additional engineering; non-standard condition for owner. COURSE OF ACTION Repaired (schedule im…

EOL Elec Platform Beam Supports

STATEMENT OF PROBLEM Additional floor support is required to support the elec. platform. schedule delay as elec platform cannot be installed until floor is poured. COURSE OF ACTION Poured floor before installing platform (schedule delay). LESSON LEARNED Capture Pontiac AA0 solution and incorporate into drawi…

Bus Duct Reuse

STATEMENT OF PROBLEM Disconnect between RE&F intent and what was stated on drawings. Increased cost of purchasing new bus duct. COURSE OF ACTION Purchased new bus duct (increased cost). LESSON LEARNED Work with AE to develop more clear expectations for reuse.

Demolition Noise Level Issue

STATEMENT OF PROBLEM The concrete was demolished using a jack-hammer, which caused some higher noise levels and led to one recordable. Also, there was a corporate safety audit that took place at the same time that identified the noise hazard. The Plant was notified of the noise and the employees were suppose to b…

Middle Bay Press Unload Area

STATEMENT OF PROBLEM Due to the Paint Shop construction, the previously available laydown space for press parts was eliminated. This was discovered after project award. Required additional design effort and a field order to provide additional pavement for laydown space. COURSE OF ACTION None LESSO…

Cam Box Supports Issue

STATEMENT OF PROBLEM Drawings lack as installed detail regarding floor support at the cam box. lack of detail drives cost in additional material, work, and direction. COURSE OF ACTION None LESSON LEARNED Work with Press Engineers to gather detailed drawings of field fixes from previous install…

scroll to top icon