-
GM Pontiac Substation W Equipment Floor Loading Issue
STATEMENT OF PROBLEM CCC received the substation equipment shop drawings from GM late in the project, at end of July. In August CCC worked with GM on the rigging plan for hoisting the new substation equipment into the penthouse. IBI performed a structural analysis of the penthouse framing steel and the hoist beam…
-
GM Pontiac Fire Alarm Design Review
STATEMENT OF PROBLEM The electrical subcontractor contracted Siemens to perform the fire alarm design. The drawings were submtited and reviewed by IBI and were also reviewed and approved by the city/fire department. However it was identified after the fact that the fire alarm drawings did not include smoke detect…
-
GM Pontiac Press Pit Lighting Fixtures
STATEMENT OF PROBLEM The lighting fixture designed for the press pit and tunnel lighting went through IBI and GM approval and the photometric calcs were discussed several times. However prior to installation, the electrical subcontractor realized that the fixture was not listed in GM OneSpec. Triangle notified CC…
-
GM Pontiac Column Coordination Log
STATEMENT OF PROBLEM Due to the amount of the utility drops at columns for this project being on the lighter side, a column coordination log was forgone and instead any and all column coordination was performed in regular 3D coordination meetings between CCC and its subcontractors. The primary reason for the colu…
-
GM Pontiac Toilet Room Basin Sinks
STATEMENT OF PROBLEM Incorrectly sized basin-style sinks were installed in the mens and womens toilet rooms, which created a code violation where the egress minimum width of 36" was impeded in the mens toilet room entrance way. The architect sized and placed the basin-style sinks at mens and womens locker rooms but …
-
GM Pontiac Overhead Doors System Design
STATEMENT OF PROBLEM The (3) blank receiving overhead doors for this project were desired to closely mimick the blank receiving doors at LGR stamping plant addition. However, it was unknown what all of the control features were or how they interfaced. It was only known that buried loops and traffic lights were re…
-
GM Pontiac Guardrails and Bollards Design
: STATEMENT OF PROBLEM Guardrails and bollards design varies for each plant based on what the plant has for existing standard and what management wants to use. Because of this, there was confusion between the team members on the type of guarding that should be used/installed. For interior guardrails protecting …
-
GM Pontiac Blank Receiving Roof Support Steel for HVU-1
STATEMENT OF PROBLEM During design of the building steel, 4 joists in the blank receiving bay were upsized to accommodate the weight of the blank receiving air handling unit (HVU-1; 17000#) in bay 22/23, based on JEG''''s input. Later in the design phase (50% MEP design), the mechanical engineer rotated and moved th…
-
Coordination of Mechanical Equipment & Site Structural Support Pads
STATEMENT OF PROBLEM: A coordination meeting between structural/civil/mechanical was held for the outdoor air rotation units which sit on concrete pads. In the meeting JEG gave the required dimensions of the pad and stated the ARU & pad should be centered within the building column bay. The pads were then designed b…
-
GM Pontiac Establishing an Elevation of Top of Floor - Impact on Process
STATEMENT OF PROBLEM During design, elevations were taken along the existing A-line floor and along the MPS building. These elevations were used to average a finish floor level for the building addition. In original design, two die cart rails ran N-S from the die wash booth to A1-line. However after the construct…
