STATEMENT OF PROBLEM CCC received the substation equipment shop drawings from GM late in the project, at end of July. In August CCC worked with GM on the rigging plan for hoisting the new substation equipment into the penthouse. IBI performed a structural analysis of the penthouse framing steel and the hoist beam…
Project Phase: Construction/Installation Delivery Method: General Contract-Prime We did not have a good plan for the floor cleaning requirements of the project. CCC was responsible for cleaning the floor slabs and eliminating the grease and oil. The team was not prepared for this level of cleaning a…