You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from GM tag

Safety Audit - Separate Vendors

8570 GM Detroit Factory Zero Phase 3 STATEMENT OF PROBLEM When have multiple different projects at the same facility. With different  delivery methods. Consider using a separate vendors  and / or subcontractors to avoid confusion with invoices and scope of work. ROOT CAUSE N/A COURSE OF ACTION The CCC team …

Safety Audit - Shutdown Kits

8570 GM Detroit Factory Zero Phase 3 STATEMENT OF PROBLEM Body shop tooling kits arriving without complete drawings and / or material. ROOT CAUSE N/A COURSE OF ACTION The CCC team and subcontractors, requested the missing information early on.  Reviewed drawings, walk the existing cells with prints prior …

Safety Setup

8560 GM GRx capacity Increase (BP-1000) STATEMENT OF PROBLEM For certain customers, especially GM, there is a lot of set up that needs to take place before a project can even start mobilization. (Safety board, PTPs, Job site safety plan, on line orientation, customer requirements, etc.) In real time, the custome…

Safety Audit - Safety Board

8570 GM Detroit Factory Zero Phase 3 STATEMENT OF PROBLEM CCC has been onsite at GM Factory Zero / DHAM for over 4 years. It was discovered that some of the contacts on the observation board and PTP's were no longer relevant. ROOT CAUSE N/A COURSE OF ACTION The CCC safety team performed an audit of active p…

Mod Section Shipping Order

8555-02 GM Factory Zero STATEMENT OF PROBLEM The Mod 1 Trim Mod sections started shipping to the plant in numerical order from Station 101-117. we discovered when we started installing the mod sections that there was only  (2) hangers on the three mod sections bolted together. This caused us to have to use chai…

K Strut Bracing

8555-02 GM Detroit Factory Zero STATEMENT OF PROBLEM With the building not being perfect at 22'6"  mid bay and 45' column to column  This caused some of the strut bracing to be either too short or too long. ROOT CAUSE We had figured that at some point in time the supplier designed their Mod sections around w…

Incomplete Drawings

8575 General Motors (GM) Ultium 2 Battery Plant STATEMENT OF PROBLEM 1. Incomplete drawings - Missing dimensions 2. OEM's like to layout based on bolt holes 3. OEM's left/arrived every 3 months - they tried to overturn decisions that had already been made. 4. Lack or coordination between OEM's in different are…

Safety Audit - toolbox talk engagement

8551.1 GM Detroit Factory Zero Phase 3 STATEMENT OF PROBLEM CCC notice that a lack of worker engagement during tool box talks ROOT CAUSE N/A COURSE OF ACTION The CCC safety team (Lucas) created a fun way to increase worker engagement. During the tool box talk to provide a written quiz with a handful of qu…

Material Handling

8575 General Motors (GM) Ultium 2 Battery Plant STATEMENT OF PROBLEM 1. Unable to locate specific material - Avaco did not have a contents list of what was in each skid this resulted in:      a. Waiting for OEM to locate material               - OEM's packed equipment from different systems on the same skid   …

Type of Bolted Connections (Channel vs Plates)

8555-02 GM Detroit Factory Zero STATEMENT OF PROBLEM Chassis Mod 1 all of the Mod sections were constructed of 8" channel. The Channels were "Toe Clipped" to an inverted "T" iron, as known the channel has a slanted surface. the supplier did not have the correct type of set-up for the Toe Clip Connection. The supp…

scroll to top icon