Project: 3208 GLWA Oakwood CSO HVAC Upgrades STATEMENT OF PROBLEM: On the GLWA provided estimate form, CCC mistakenly included base bid budgets for roofing work within the allowance lines instead of in the base bid section. ROOT CAUSE: Misinterpretation of the allowance bid category which was "Roof Repairs". …
Project Phase: Design Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: The original project scope required for all grade-mounted HVAC units for convenience of maintenance. However due to the higher cost of grade-mounted units, CCC team qualified their original bid with all rooftop u…