Liquidated Damages

Project Phase- Construction/Installation Delivery Method- General Contract-Prime The contract did not have stated liquidated damages for penalty or delay. This left CCC open to actual damages.

Cleaning floors after demolition activity

Project Phase: Construction/Installation Delivery Method: General Contract-Prime We did not have a good plan for the floor cleaning requirements of the project. CCC was responsible for cleaning the floor slabs and eliminating the grease and oil. The team was not prepared for this level of cleaning a…

Bus Shutdown

Project Phase: Design Delivery Method: General contract-Prime Bus shut downs were not part of the master schedule. This caused a lot of heart ache with the plant as bus plug shutdowns affected other contractor''''s work. The owner did not want bus shutdowns within the master schedule due to anticipated chan…

Demolition Tagging Procedures

Project Phase- Construction/Installation Delivery Method- General Contract-Prime As part of the scope we were to identify and mark utilities to be air gapped for make safe demolition. The routing of these utilities, plant logistics and infrastructure in place made the identification and marking of these uti…