You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from CCC tag

Site Representation Prior to Construction

Project Phase- Construction/Installation Delivery Method- General Contract-Prime Project had a unique schedule where the main work was not to take place until 10 months after contract award. The majority of that time was for planning the work to be completed. We never intended on having a full time CCC staff memb…

Demolition Tagging Procedures

Project Phase- Construction/Installation Delivery Method- General Contract-Prime As part of the scope we were to identify and mark utilities to be air gapped for make safe demolition. The routing of these utilities, plant logistics and infrastructure in place made the identification and marking of these uti…

Cleaning floors after demolition activity

Project Phase: Construction/Installation Delivery Method: General Contract-Prime We did not have a good plan for the floor cleaning requirements of the project. CCC was responsible for cleaning the floor slabs and eliminating the grease and oil. The team was not prepared for this level of cleaning a…

Bus Shutdown

Project Phase: Design Delivery Method: General contract-Prime Bus shut downs were not part of the master schedule. This caused a lot of heart ache with the plant as bus plug shutdowns affected other contractor''''s work. The owner did not want bus shutdowns within the master schedule due to anticipated chan…

scroll to top icon