You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from CCC tag

Precast Plank Installation Within Building

Project Phase: Construction Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: Precast plank installation over toilet rooms, within building after steel was erected. Based on the lead time of the precast the lid had to be installed after the roof steel was erected and there was …

Floor Tolerances for Machine Foundation Installation

Project Phase: Construction/Installation Delivery Method: Facilities Maintenance Statement of Problem: Floor was out of level to the extent that it made it difficult to set machine foundations within tolerance.

Union Issue - Loss of Productivity / Schedule Impact

Project Phase- Construction/Installation Delivery Method- General Contract-Prime CCC (Prime) and Demo Contractor Adamo (Subcontractor) were contracted to perform a Demo Strip out of the Chicago Assembly Plant Body Sides Bldg and Body Shop.  Over 1,500,000 sf of Demo to be completed in 7 days.  Almost unreal…

Environmental Remediation Subcontractor Management

Project Phase- Construction/Installation Delivery Method- General Contract-Prime Make sure that environmental subcontractor understands what the scope of work is and that they patrol the areas themselves instead of CCC running their crews. The environmental sub (AMS) did not fully understand the scope of th…

Electrical Room Door Swing

Project Phase: Construction/Installation Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: After substantial completion, the Owner''s facility maintenance person questioned the door swing of the electrical room, which swings into the room. He cited that per building code, any electrical roo…

Shift Turnover

Job #3007  Ford Chicago Assembly - Demolition STATEMENT OF PROBLEM Shift turn overs were not formalized, it seemed like it was a bit of a free for all. ROOT CAUSE Did not outline a standard shift turnover meeting/huddle which impacted communications from shift to shift. COURSE OF ACTION No action was taken …

Roof Maintenance Access

Project Phase: Construction Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: During the design phase of the BP-06 architectural build out, the height of the mezzanine in relation of the roof steel and height of the low roof did not allow for the chain hoist/rail within the high ba…

3D BIM Coordination

Project Phase: Construction Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: The laboratory project involved a lot of utilities within the ceiling space. At bid time, the Owner did not accept a bid alternate for developing a 3D model deliverable. The building was designed in mostl…

Document Conditions Before Demolition

Project Phase - Construction/Installation Delivery Method- General Contract-Prime After demolition completion, the owner came back and stated that CCC had damaged some things, and we had no way of knowing who broke it / prove them wrong.

Floor Patching

Project Phase- Design Delivery Method- General Contract-Prime There was a T&M allowance for floor patching. A week before job start, Owner notified CCC we would be doing the patching. Floor patching material wasn''t approved until a few days prior to the start of shutdown. The material wasn''t going to …

scroll to top icon