STATEMENT OF PROBLEM Precision surveying requirements not clearly defined in contract documents; Contractor not performing as frequently with signed-off documentation between Owner-Contractor-AE. Unclear expectations to the contractor; potential cause for errors. COURSE OF ACTION None LESSON LEARN…
STATEMENT OF PROBLEM Many Subcontractors are not familiar with 3D Model design and/or design build. The limited pool of contractors who can bid GM work due to NMA and Safety Guidelines is very limited. Problem is learning curve to train subcontractors to build per model without the proverbial "shoving the require…
STATEMENT OF PROBLEM Missed from original bid documents, not matching Pontiac drawings; Late information from Owner, after contract award; Inadequate detail on engineer''''''''s drawings for routing, material, and details. Schedule impact; increased cost due to field order. COURSE OF ACTION Field ordere…