STATEMENT OF PROBLEM During design of the site, civil designed for an exterior grading elevation which was higher than the top of the grade beam elevation at the NE corner of the building. At this location there is a narrow gap between the building grade beam and the ring road (about 3''''). Originally a curb was no…
STATEMENT OF PROBLEM At bid time CCC received the 1950 Albert Kahn facility record drawings of the plant. This set had two foundation drawings, showing two different column foundation types for the plant. One drawing showed all footings, one drawing showed all caissons. It was unknown by GM which was the as-built…
STATEMENT OF PROBLEM Before the cooling tower system was turned over to the plant, an oily sheen was discovered in the basins by GM. CCC mitigated the issue with oil socks but it was brought up by the plant on why the filter was not running/filtering the oil. This was because the filter is not meant to filter oil…
STATEMENT OF PROBLEM During design of the building steel, 4 joists in the blank receiving bay were upsized to accommodate the weight of the blank receiving air handling unit (HVU-1; 17000#) in bay 22/23, based on JEG''''s input. Later in the design phase (50% MEP design), the mechanical engineer rotated and moved th…
STATEMENT OF PROBLEM For this project a new, welded steel oily wastewater tank was provided in the scrap tunnel in lieu of relocating an existing tank, at no cost to GM. The new tank shop drawings did not include for a manway. The shop drawings were submitted, reviewed, and approved by the EOR. The tank was fabri…
STATEMENT OF PROBLEM The GM process team stated they wanted 36" wide clearance for all metal stairs in a design meeting. When IBI designed the stairs they made the tread 36" wide. However, the inner grab bars which project from the outer guardrail impede on that clearance (only 32" clearance). This was deemed a n…
STATEMENT OF PROBLEM Incorrectly sized basin-style sinks were installed in the mens and womens toilet rooms, which created a code violation where the egress minimum width of 36" was impeded in the mens toilet room entrance way. The architect sized and placed the basin-style sinks at mens and womens locker rooms but …
STATEMENT OF PROBLEM During the design process CCC was provided with a Rotem drawing with several sheets detailing the press foundation requirements. An enlarged elevation called for a "can" cast into the pier to allow for bolting the press anchor rod (hand hole). The drawing showed the can height at 300mm. Howev…
STATEMENT OF PROBLEM CCC received the substation equipment shop drawings from GM late in the project, at end of July. In August CCC worked with GM on the rigging plan for hoisting the new substation equipment into the penthouse. IBI performed a structural analysis of the penthouse framing steel and the hoist beam…
: STATEMENT OF PROBLEM Guardrails and bollards design varies for each plant based on what the plant has for existing standard and what management wants to use. Because of this, there was confusion between the team members on the type of guarding that should be used/installed. For interior guardrails protecting …