Lock Out Tag Out

Project Phase:- Construction/Installation Delivery Method- General Contract-Prime A significant amount of lock out tag out (LOTO) was required early in the project. The effort to complete this took longer than anticipated affecting schedule. Lack of knowledge from Safety and Supervision of the LOTO process …

Press Plate Deep Pour Epoxy Grouting Issues

STATEMENT OF PROBLEM: CCC performed deep pour of Micor epoxy grout between the press plates and the concrete piers, for 20 plates. The epoxy grout was required to have a compressive strength of 10,000PSI. CCC constructed a headbox and used safety cones for the pour, following procedure as provided by Micor rep. H…