STATEMENT OF PROBLEM Provided a high level of detail of the existing framing and utility conditions that would not be clear on the as-built drawings. Highlighted areas where framing and utilities could go without impacting process equipment. Reduced engineering time and field interference. COURSE OF ACTION …
STATEMENT OF PROBLEM A checklist was not used to facilitate the turnover of the press bay from Facilities to the Press group. Caused some discussions to be missed. COURSE OF ACTION None LESSON LEARNED Institute the buy-off checklist with meeting on ALL press projects.
STATEMENT OF PROBLEM Crane inspection was not performed prior to turnover. Without an inspection it is difficult to determine if wear or maintenance issues on the crane were from construction or from previous plant use. COURSE OF ACTION None LESSON LEARNED An inspection should be done by the facility contrac…
STATEMENT OF PROBLEM The level on the drawings was good, but could have been a bit heavy. No major impact from the level of details on the bridging documents. COURSE OF ACTION None LESSON LEARNED Because of the level of detail known about the press and supporting details, it allowed for more c…
STATEMENT OF PROBLEM Design was not finalized early enough in the project. Caused design iteration. COURSE OF ACTION None LESSON LEARNED Put more emphasis on the fact that a scrap handling design is critical path.
STATEMENT OF PROBLEM Physical lay down space was less than desired. This is pretty common with press relocation work where the bay of work is the only space available for construction. Physical lay down space was less than desired. This is pretty common with press relocation work where the bay of work is the only…
STATEMENT OF PROBLEM The compressed air demand for the two presses and FOL equipment changed after the contract aware. This was in part due to a new system late that was still being worked out in Fairfax, and all of the necessary testing was not complete prior to award. Extra effort for engineering to run through…
STATEMENT OF PROBLEM The concrete was demolished using a jack-hammer, which caused some higher noise levels and led to one recordable. Also, there was a corporate safety audit that took place at the same time that identified the noise hazard. The Plant was notified of the noise and the employees were suppose to b…
STATEMENT OF PROBLEM Due to the Paint Shop construction, the previously available laydown space for press parts was eliminated. This was discovered after project award. Required additional design effort and a field order to provide additional pavement for laydown space. COURSE OF ACTION None LESSO…
STATEMENT OF PROBLEM Some confusion over fire protection in the infill area. It was included in the South Bay, but not included in the Middle Bay. Scope delineation was not clear, and wasn''''t addressed until after award. Resulted in a field order. COURSE OF ACTION None LESSON LEARNED Needs t…