Project Phase: Construction/Installation Delivery Method: General Contract-Prime We did not have a good plan for the floor cleaning requirements of the project. CCC was responsible for cleaning the floor slabs and eliminating the grease and oil. The team was not prepared for this level of cleaning a…
STATEMENT OF PROBLEM: No determination was provided from KUKA on the anchoring of the Kawasaki Robot RTU (7th axis robot) until the equipment arrived. It was then learned that the holes in the bases were suitable for 5/8 mechanical anchors and not 5/8" chemical anchors since the holes in RTU base were not large enoug…