Middle Bay Laydown Area
print icon
  STATEMENT OF PROBLEM
Physical lay down space was less than desired. This is pretty common with press relocation work where the bay of work is the only space available for construction. Physical lay down space was less than desired. This is pretty common with press relocation work where the bay of work is the only space available for construction. Spatial constraints, and potential safety with limited walking space.

COURSE OF ACTION
None

LESSON LEARNED
Consider providing a drawing during bidding that shows the available limits.