  STATEMENT OF PROBLEM
Missed from original bid documents, not matching Pontiac drawings; Late information from Owner, after contract award; Inadequate detail on engineer''''''''s drawings for routing, material, and details. Schedule impact; increased cost due to field order.

COURSE OF ACTION
Field ordered for installation (cost and schedule impact).

LESSON LEARNED
Work with Central Layout to provide in the process layout, if required.