As Built Conditions Expectation Issue
print icon

STATEMENT OF PROBLEM
Need clear expectations of what items are existing. What is to remain, or be removed. Confusion to bidders; cost increase due to field orders.

COURSE OF ACTION
None

LESSON LEARNED
Work more closely with AE''''''''s to capture as-built conditions at project completion, and to verify conditions during initial site reviews.