May 07, 2021
STATEMENT OF PROBLEM Should have been coordinated with "Owner" prior to issuing bid drawings; Lazy approach by team to just "copy"; Information was known, and could have been committed to. Many DCRs; schedule delays; cost increase due to field orders COURSE OF ACTION Field orders (schedule delays, cost impacts) LESSON LEARNED Work more closely with Press Engineers to reduce (or remove) these types of notes from the drawings. |