Verify With Owner Notes
print icon
  STATEMENT OF PROBLEM
Should have been coordinated with "Owner" prior to issuing bid drawings; Lazy approach by team to just "copy"; Information was known, and could have been committed to. Many DCRs; schedule delays; cost increase due to field orders

COURSE OF ACTION
Field orders (schedule delays, cost impacts)

LESSON LEARNED
Work more closely with Press Engineers to reduce (or remove) these types of notes from the drawings.