Job #3333 Bluewater Gas Kimball Compressor Station STATEMENT OF PROBLEM: An existing foundation was identified in a post bid walk as a footing that needed to be removed and replaced. There were no drawings available, however when details eventually were released, the owner indicated that they were not paying for …
Project Phase: Construction Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: The lab planner architect specified point-of-use fixture types for all of the lab gases in the project. There were numerous fixtures that were to be installed at the wall with the fixture protruding horizontally fro…