Site Utilities Placed Out of Sequence

CCC Job #3374 StarPlus Energy Kokomo Battery Plant STATEMENT OF PROBLEM: Normally UG site utilities would be installed during the site preparation phase prior to placement of foundations.  In this project the utility and mechanical plans were still under development when foundation work started.  This led to UG w…