FCA Value Analysis Process

STATEMENT OF PROBLEM: There were close to 200 quotes that were submitted for extra work over the life of this project. Out of all of these quotes, only 14 of them had a scope of work and/or drawings that we received from the customer to bid off. FCA also used a third party company (Faithful & Gould) to perform detail…